SpectraLink Corporation 
T1 Remote Module Installation 
 
Link WTS – Link 3000 MCU 
7.3  Site Preparation Checklist 
If upon arrival the SpectraLink installer determines that the pre-installation work has not 
been completed correctly, the installer has two options: 1) the installer can leave the site 
and reschedule the installation when the action items have been completed or corrected, 
or 2) the installer can assist in preparing the site, and thus spend additional time 
installing the system.  Because of the additional cost incurred by SpectraLink in 
executing either option, the customer will be billed for the additional time at our 
standard hourly rate plus expenses. 
Please be sure the following items are completed.  
 
MCU location prepared.  Typically the MCU is installed in the telephone equipment 
room.  This location must have sufficient rack or backboard space and power 
available. 
 
Two-pair wires are run to each of the Base Station locations as designated on the 
building floor plans.  Use Level 3 cable for lengths up to 3,500'; Level 4 for lengths 
up to 6,000'. 
 
The Base Station cables are terminated with RJ-45 crimp-on plugs at the designated 
locations. 
 
One (or two) cross-connect block(s) are installed for every Interface Module and 
connected with a 25-pair Telco cable terminated with an RJ-21 male connector at the 
MCU location. 
 
The Base Station cables are terminated at the appropriate cross-connect blocks. 
 
Analog or digital ports, one per Wireless Telephone, from the switch are terminated 
at the appropriate cross-connect block and the block is labeled with the extensions. 
 
A dedicated dial line (MB) is available with an RJ-11 jack for the diagnostic modem. 
 
An IBM-compatible PC is available to serve as the Operator’s Console for system 
administration. 
 
A system administrator is designated for the SpectraLink system.  This person should 
be present for the installation.  The SpectraLink installer will provide system training 
to the system administrator on the day following the installation. 
When this checklist is completed please sign, date, and fax to:  
(Install Coordination 303-449-7016) 
Signature: _______________________________________  Date: _________________ 
If you have any questions regarding the installation procedure, please call: 
SpectraLink Customer Support Hotline 1-800-775-5330
 
(Monday through Friday, 7 AM to 6 PM MT). 