35
3. Finally power on the Paragon II base tier.
4. Perform a partial reset of the database on the impacted switches. For
example, if you swap the switches connected to the base tier, perform
the partial reset on the base tier. If you swap the switches connected
to the second tier, perform the partial reset from the second tier to the
base tier.
the partial reset on the base tier. If you swap the switches connected
to the second tier, perform the partial reset from the second tier to the
base tier.
Installing the Paragon P2-UMT832S Stacking Unit
1. Make sure all Paragon switches are powered OFF.
2. Connect a power cord to a Stacking Unit.
3. Connect one end of a stacking cable to ʺExpansion Port Outʺ on the
back of the Stacking Unit. Connect the other end of the cable to
ʺExpansion Portʺ on the Main Unit.
ʺExpansion Portʺ on the Main Unit.
4. Power ON all Paragon switches.
5. On the front panel of the Main Unit:
a. Press the FUNC button and use the and buttons to select
ʺStacking Support.ʺ Press the ENT button to confirm the
selection.
selection.
b. Select the total number of Stacking Units (3 units maximum) and
press the ENT button.
6. On the front panel of the Stacking Unit:
a. Press the FUNC button and use the and buttons to select
ʺSet Stack ID.ʺ Press the ENT button to confirm the selection.
b. Assign the Stacking Unit ID using the and buttons. (Each
Stacking Unit MUST HAVE A UNIQUE ID [1‐3], and sequential
order is not necessary).
order is not necessary).
7. Press the ENT button to save the ID setting.
8. Power OFF all units.
9. Power on the Stacking Unit.
10. Power on the Main Unit.
Installing the Paragon P2-UMT1664S Stacking Unit
1. Make sure all Paragon switches are powered OFF.
2. Connect a power cord to a Stacking Unit.
3. Connect the Main Unit with the Stacking Unit using two stacking
cables.