Chassis Switch Management 
473
 Managed Switches
After you preconfigure a member type for a specific slot number, attaching a blade with a 
different blade type for this slot number causes the chassis to report an error. The show 
chassis
 command indicates a configuration mismatch for the new member and the ports on 
that slot do not come up. To resolve this situation, you can change the slot number of the 
mismatched unit or delete the preconfigured blade type using the no member <unit-id> 
command. 
When you add a new blade to the chassis, the chassis applies either the preconfigured 
configuration or the default configuration. The following table lists the events that occur when 
the chassis compares the preconfigured configuration with the new member.
Table 3.  Preconfigured blade compared to chassis configuration  
Same Blade Type
Same Slot
Result
Yes
Yes
The chassis applies the configuration to the preconfigured new 
blade and adds the blade to the chassis.
Yes
No
The chassis applies the default  configuration to the new blade and 
adds the blade to the chassis.
No
Yes
The chassis considers it a configuration mismatch. All of its ports 
retain detached mode and no configuration applies to the member.
No
No
The chassis applies the default  configuration to the new blade and 
adds the blade to the  chassis.
Move the Supervisor to a Different Blade
Only one blade can be the supervisor in one chassis. But you can move the supervisor to 
another blade if you must do so. In the chassis, only the blades in slot 1 or slot 2 can be used 
as the supervisor, so two blades are required and they are in slot 1 and slot 2.
This example is provided as CLI commands and a web interface procedure.
CLI: Move the Supervisor to a Different Blade
1. 
Using the movemanagement command, move the master to a different unit number. 
The operation takes between 30 seconds and 3 minutes depending on the 
configuration. The command is movemanagement <fromunit-id> <tounit-id>.
2. 
Make sure that you can log in on the console attached to the new supervisor. Use the show 
switch
 command to verify that all blades rejoined the chassis. 
3. 
NETGEAR recommends that you reset the chassis with the reload command after moving 
the supervisor.