Monessen Hearth BBV400 User Manual

Page of 40
62D4036
11
BBV, SBV Series Natural Vent Gas Fireplaces
VENT INSTALLATION
FIRESTOPS
  Locate chimney centerline dimension from a com-
bustible back wall. Figures 2 & 3. Minimum firestop 
dimensions are found in the vent manufacturer’s in-
structions. Clearances to combustibles may also be 
found on the sides of the flue sections.
  Avoid  cutting  any  load-bearing  framing  members. 
Figures 6 & 7
To position firestop refer to Figures 6 & 7. Only one firestop 
is required per frame.
FP2020
firestop
10/08
Nails
Firestop 
Spacer
Joist
FP2020
Nails
Firestop 
Spacer
Joist
Figure 6 - 
Install Firestop in Attic
Figure 7 - 
Install Firestop 
in Ceiling
NOTICE: When installing in a chase, you should insu-
late the chase as you would the outside walls of your 
home.  This  is  especially  important  in  cold  climates. 
Insulation  should  be  considered  a  combustible  ma-
terial. Maintain proper clearances to all combustible 
materials.
NOTICE:  Treatment  of  firestops  and  construction  of 
the  chase  may  vary  from  building  type  to  building 
type.  These  instructions  are  not  substitutes  for  the 
requirements  of  local  building  codes. You  must  fol-
low all local building codes.
TERMINATE THE PIPE
  Maintain  proper  clearance  to  the  roof  using  the 
chart below.
  Vents  shall  terminate  at  least  8’  from  a  vertical 
wall.
  Maintain  2’  minimum  clearance  to  any  other  gas 
terminations or plumbing vents, as measured from 
the outside edge of the terminations or vents.
H
X
12”
FP2405
min  chimney ht
Figure 8 - 
Minimum Chimney Height
FP2405
Termination Height Table
Use this table to determine the minimum height avove     
the roof
 
Minimum Height
  Roof Pitch 
Feet 
Meters
  Flat to 7/12 
0.3
  Over 7/12 to 8/12 
1.5 
0.46
  Over 8/12 to 9/12 
0.61
  Over 9/12 to 10/12 
2.5 
0.76
  Over 10/12 to 11/12 
3.25 
0.99
  Over 11/2 to 12/12 
1.22
  Over 12/12 to 14/12 
1.52