Initial Installation
QUALIFIED INSTALLERS ONLY
24
Figure 35: Cathedral Ceiling Support Box Leveling.
1.  Follow  installation  steps  1  &  2  under  i
nitial
 
i
nStallation
 - v
ertical
 i
nStallation
.
2.  Using the plumb bob, mark the centerline of 
the venting system on the ceiling and drill a 
small hole through the ceiling and roof at this 
point. From the roof, locate the drill hole and 
mark  the  outline  of  the  “Cathedral  Ceiling 
Support Box”.
3.  Remove  shingles  or  other  roof  coverings  as 
necessary to cut the rectangular hole for the 
“Support  Box”.  Cut  the  hole  ⅛”  larger  than 
the “Support Box” outline.
4.  Lower the “Support Box” through the hole in 
the roof until the bottom of the “Support Box” 
protrudes at least 2 inches (5 cm) below the 
ceiling. Align the “Support Box” both vertically 
and  horizontally  with  a  level  as  shown  in 
Figure 35. Temporarily tack the “Support Box” 
in the place through the inside walls and into 
the roof sheathing.