INSTALLATION
6
YORK INTERNATIONAL
FORM 115.20-NOM2 (105)
7
YORK INTERNATIONAL
INSTALLATION
FORM 115.20-NOM2 (105)
Prior to connecting to the fan coil, 
all external piping must be purged 
of debris.
When  connecting  piping  or  valve 
kits to fan coil units, do not bend or 
reposition the coil header tubing for 
alignment purposes. This could cause 
a tubing fracture resulting in a water 
leak when water pressure is applied 
to the system.
Many valve packages will not phys-
ically  allow  all  components  to  fit 
over an auxiliary drain pan. It is the 
installers responsibility to ensure ad-
equate condensation prevention. The 
installer must also ensure that there 
is no condensate drippage onto elec-
trical components beneath insulated 
components. 
PRECAUTIONS
 1.   Flush all field piping prior to connection to remove 
all debris.
 2.   Use  wet  cotton  rags  to  cool  valve  bodies  when 
soldering.
 3.   Open all valves (mid-way for hand valves, manually 
open on motorized valves) prior to soldering.
 4.  When soldering to bronze or brass, heat the pip-
ing while in the socket/cup and begin introducing 
the solder when the flux boils rapidly. Avoid direct 
flame into the solder joint.
 5.   Heat can only be applied to the cup of the valve body 
for a minimal time before damage occurs (even with 
the use of wet rags.
 6.  Avoid rapid quenching of solder joints, as this will 
produce joints of inferior quality.
 7.  The valve package will not support the weight of 
the connecting pipes. All pipes, which are connected 
to the units, must be completely supported prior to 
connection to the unit.
 8.   Provisions must be made for expansion and con-
traction  of  piping  systems. All  horizontal  and 
vertical risers, including runouts, must be able to 
withstand significant movement with temperature 
changes. Failure to do so will result in damage and 
failure of piping, fittings and valves throughout the 
building.
 9.   Never insulate the heads or motorized portion of 
control valves. Damage can occur in the form of 
excessive  heat  build  up  and  interference  to  the 
operation and moving parts will result.  
10.  All piping made in the field should be installed with 
consideration of additional space for any electrical 
routing that may be required.
 11. Hydronic systems are not designed to hold pres-
surized air and should only be tested with water.
After the system has been proven leak free, all lines and 
valve control packages must be insulated as specified 
on the building plans.
These units are provided with six (6) mounting holes 
(see drawings for details). Metal washers and nuts of 
the proper size are to be provided by the installer. When 
necessary, use shims to obtain the proper level. This will 
ensure that the condensate will drain from the unit.
PIPING
These units employ a hydronic coil designed for use 
with either hot or chilled water. 
All piping must be adequately sized to meet the design 
water flow requirements as specified for the specific 
installation. Piping must be installed in accordance with 
all applicable codes. 
PIPE SIZES
All models except YHYB/YPHYB:
•  HW/CW coils are 3/8" OD tubing.
•  Tubing connections are 5/8" OD.
Models YHYB/YPHYB:
   •   HW/CW coils are 1/2" OD tubing.
   •  Tubing connections are 7/8" OD.
Manual air vents are provided standard on all coils
All chilled water piping must be insulated to prevent 
condensation.