Emerson Series 3000 MVD User Manual
186
Micro Motion
®
Series 3000 MVD Transmitters and Controllers
Measurement Performance
Figure 21-2
Meter verification test, original version – Display
21.3.3
Running Smart Meter Verification
To run a Smart Meter Verification test:
•
With ProLink II, see Figure 21-3.
•
With the display, see Figure 21-4.
•
With the Communicator, see Figure 21-5.
Note: If the custody transfer application is installed and the transmitter is secured, you can run a
Smart Meter Verification test with outputs set to Continue Measuring or Fault. Last Measured Value
is not available. See Section 19.3 for detailed information.
Smart Meter Verification test with outputs set to Continue Measuring or Fault. Last Measured Value
is not available. See Section 19.3 for detailed information.
Note: If you start a Smart Meter Verification test from ProLink II or the Communicator, and the
outputs are set to Last Measured Value or Fault, the transmitter display shows the following message:
outputs are set to Last Measured Value or Fault, the transmitter display shows the following message:
SENSOR
VERFY/x%
VERFY/x%
Start Meter Verify
Progress . . . . . . . . . x%
PASS
ABORT
FAIL
Select
Set Uncertainty Limit
(1)
Maintenance Menu >
Meter Verification >
Meter Verification >
Set output behavior
Proceed?
Yes
(1) Enter the uncertainty limit as a decimal value,
e.g., 0.0400 (4%).