ID
Task Name
Projected
Actual
Start
End
Start
End
72
Batch Application Tests Can Start
06/07/98
06/07/98
73
Perform Critical Application Batch Tests
06/07/98
08/16/98
74
Non-critical Application Batch Tests
08/16/98
09/21/98
75
Refine New OS/390/DFSMS Standards
05/10/98
08/16/98
76
Identify Application Interfaces
06/14/98
08/02/98
77
Refine & Repeat Batch Application
Conversion
05/10/98
08/16/98
78
Switchover Preparation
07/19/98
09/21/98
79
File Migration
07/19/98
08/16/98
80
Develop Switchover File Migration Specs
07/19/98
08/02/98
81
Develop Switchover File Migration
Procedures
08/02/98
08/16/98
82
Switch Rehearsal Can Start
08/16/98
08/16/98
83
Rehearse Switchover File Migration
08/16/98
08/17/98
84
Production Tests
08/17/98
09/21/98
85
Perform Production Tests
08/17/98
09/21/98
86
Actual Conversion
08/17/98
09/21/98
87
Convert Development Code
08/17/98
08/30/98
88
JCL Supply For Last Mass Conversion
08/22/98
08/23/98
89
Last Mass JCL Conversion
08/24/98
08/30/98
90
Fix & Freeze
″ 
JCL
08/24/98
09/21/98
91
Program Supply for Last Mass Conversion
09/09/98
09/10/98
92
Last Mass Program Conversion
09/11/98
09/12/98
93
Freeze & Fix
″ 
Programs
09/11/98
09/21/98
94
Switchover Can Start
09/21/98
09/21/98
95
OS/390 Switchover
09/21/98
10/23/98
96
Final Switchover Preparation
09/21/98
09/26/98
97
Actual Switchover Weekend
09/26/98
09/26/98
98
Assist OS/390 Operations
09/28/98
10/23/98
99
Project End
10/23/98
10/23/98