Lucent Technologies 555-233-115 User Manual

Page of 502
DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r  
555-233-115  
Issue 1
April 2000
Multicarrier G2 Universal Module to R8r EPN 
5-83
Critical Reliability 
5
Figure 5-24. Location of P1 and P2 Connectors
Prepare the New A and B Position Carriers
1. Inspect the new carriers for any damage. Verify that the backplane pins 
are not bent.
2. Place the expansion control carrier on the floor so that the rear of the 
carrier faces up.
3. Install the CFY1 current limiter (CURL) on the “A” carrier to the pin-field 
block marked “CURL.” The CURL is inserted with the components on the 
left side as viewed from the rear.
4. At the rear connector panel, determine which connectors will have a cable 
attached, and install a 4B cable retainer on each of these connectors.
Figure Notes
1. Rear of Control Carrier 
2. P2 Connector
3. P1 Connector