Multicarrier G2 Universal Module to R8r EPN 
5-84
Critical Reliability 
5
Install the New A and B Position Carriers
1. Install the J58890AF Expansion Control Carrier in position “A” by lining up 
the plastic alignment tips on the top rear of the carrier with the screw holes 
in the cabinet. These alignment tips will support the carrier while the 
screws are being replaced. Ensure that the power cords are properly 
placed in the slots at the sides of the carrier.
2. Fasten the carrier into position with 4 self-tapping screws saved from the 
removal of the old carrier.
!
CAUTION:
Carefully realign the threads on the self-tapping screws by turning 
them counterclockwise 1 turn before tightening them to avoid 
stripping the threads out of the framework.
3. Behind the carrier in a “DEFINITY style” cabinet, replace the 2 screws 
saved from the removal of the old carrier.
4. Install the J58890BB-3 port carrier in position “B” by lining up the plastic 
alignment tips on the top rear of the carrier with the screw holes in the 
cabinet. These alignment tips support the carrier while the screws are 
being replaced. Ensure the power cords are properly placed in the slots at 
the sides of the carrier.
5. Fasten the carrier into position with 4 self-tapping screws saved from the 
removal of the old carrier.
6. Connect the “P2” and “P1” (large and small) connectors to the “A” carrier. 
Snap the connector lock into place to ensure the connection is properly 
made. See 
.
7. Connect the “P1” (small) connector to the “B” carrier. To get enough slack 
in the cables, cut the tie wrap holding the intercabinet cables from the 
upright in the area of the carrier being installed. Snap the connector lock 
into place to ensure the connection is properly made.
8. Connect the 8 ground straps from the “D” carrier to the new “A” carrier. 
See 
. These straps were left connected to the “D” carrier.
9. Connect the 8 ground straps from the “C” carrier to the new “B” carrier. 
These straps were left connected to the “C” carrier.
10. Install the 8 ground straps between the new “A” and “B” carriers. These 
straps were removed from the old carriers.
11. For an AC-powered expansion control carrier, install the 2 new carrier 
ground straps. One strap connects ground point “1” to the A-carrier frame 
(on the right side), and the other connects ground point “8” to the A-carrier 
frame (on the left side).
NOTE:
DC-powered carriers do not use these carrier ground straps.