APC galaxy 9000 User Manual

Page of 40
34006451EN/AC
 - Page 21
Installation
Right cubicle of a parallel UPS with SSC    
Cables connected by lugs to 100 x 10 mm copper terminals and 14 mm diameter holes.
Height of connections relative to floor:
– load: 410 mm;
– remote relay board: 1030 mm.
cross-section AA
front view
APOZ
board
inverter
stack
inverter
stack
inverter
stack
spacing
uprights
cable
tie bar
air extraction
air
admission
air
admission
connection
from below
trough (if applicable)
rear
front
power cable routing via the bottom
remote relay board
load
cable tie bar
remote relay board
A
A
XR7
XR6
XR5
XR9
XR8
XR4
XR2
XR1
XR3
L1 L2 L3
N
XM133
XM136
XM137
on
off
Q5N
earth
bar
transformer
card
cage
card
cage
ACPZ
board
load