Prepare - 34
PR95 Operator’s Manual
Plan Burst Path
CMW
Plan Burst Path 
Plan the burst path, from entry to end, before job begins. Locate the entire route of the pipe to be replaced 
to ensure a straight path. Expose all crossing or parallel utilities within 18” (500 mm) of the pipe being 
burst. Visually verify that bursting head does not damage utility.
Prepare Jobsite
Mark Burst Path 
Mark your planned burst path with flags or paint.
Jobsite hazards could cause death or serious injury. Use 
correct equipment and work methods. Use and maintain proper safety 
equipment.
NOTICE: 
Cutting high voltage cable can cause electrocution. Expose lines by hand before digging.
All vegetation near operator’s station must be removed. Contact with trees, shrubs, or weeds during 
electrical strike could result in electrocution.