GE CSB9120SJSS Installation Instruction

Page of 20
6
Installation Preparation
Preparation 
WITHOUT
 an Accessory Storage Drawer
PREPARE THE OPENING (cont.)
Installation over a GE/Monogram 
Warming Drawer:
NOTE: Additional clearances between the cutouts 
may be required. Check to be sure the oven supports 
above the Warming Drawer location do not obstruct 
the required interior depth and height. See Warming 
Drawer installation instructions for details.
30s
23-1/2s
25-1/4s
17-1/2s
2
s
 Min. 
(3
s
 Recommended)
Per Warming 
Drawer 
Requirement
Construct 
Solid Bottom 
Min. 3/8s 
Plywood 
Supported 
by 2 x 4 or 2 x 
2 Runners all 
Four Sides
PREPARE THE OPENING
The Advantium 120V can be installed in 
combination with other GE/Monogram appliances. 
Always follow each product’s Installation 
Instructions to complete the installation.
Single Advantium 120V Installation:
Order a 30s wide single oven cabinet or cut the 
opening in a wall to the dimensions shown.
•  Allow 2-1/8s case trim overlap on the sides, 
1-1/16s overlap on the top and 7/8s overlap 
on the bottom of the opening for all models.  
•  Oven overlaps will conceal cut edges on all sides 
of the opening.
When installed over a single oven or a warming 
drawer, allow at least 2s between the two 
openings. This separation will provide clearance 
for bottom overlap of the Advantium 120V and the 
other appliance overlaps.
Construct a solid oven floor of 3/8s min. thick plywood 
supported by 2 x 4  or 2 x 2 runners on all sides.
•  The support must be level and rigidly mounted, 
flush with the bottom edge of the cutout.
30s
23-1/2s
25-1/4s
17-1/2s
Construct 
Base 
Min. 3/8s 
Plywood 
Supported 
by 2 x 4 or 
2 x 2 Runners 
all Four Sides