8. Maintenance
8.1 Maintenance configuration
Single-unit or single modular UPS 
(figure 25)
  
Caution:
- work should be carried out in accordance with applicable safety regulations;
- to avoid interrupting the load, the various switching operations must be carried out in the correct order. Operations 
are explained in diagrams placed next to the switches.
Multi-bypass modular UPS 
(figure 26)
  
Note:
It is strongly advised to call on our after-sales support department for these operations.
During maintenance, the UPS must be isolated 
from Mains 1 and 2, the battery and the load.
– inverter isolation
Proceed in the following order:
– shut down the inverter (press the "inverter off" 
button for 
seconds),
– close bypass switch Q3BP,
– open isolating switches Q5N, Q4S, QF1 and 
Q1.
The UPS is powered down once the capacitors 
have discharged (a few minutes);
– start-up
Following servicing, proceed in the following 
order:
– close switch Q1, then after approximately ten 
seconds, switches QF1, Q5N and Q4S,
– open bypass switch Q3BP,
start the inverter (press the "inverter on" 
button
).
Fig. 25
Prior to servicing a given UPS, it must be isolated 
from Mains 1, Mains 2, its battery and the load 
outputs of the other UPSs (in this case, never 
operate the Q3BP switches in the units).
– isolate the UPS
Proceed in the following order:
– shut down the inverter (press the "inverter off" 
button
for three seconds);
– open isolating switches Q5N, QF1, Q4S and 
Q1 in the unit.
The UPS is de-energised once the capacitors 
have discharged (a few minutes).
– start-up
Once servicing is completed, proceed in the 
following order:
– close Q1, then QF1, Q4S and Q5N;
– start the inverter (press the “inverter on” 
button
).
Fig. 26
Q1
Q5N
QF1
Q3BP
Q4S
load
battery
inverter
mains 1
rectifier-
charger
static switch
mains 2
7
6
Q1
Q5N
QF1
Q3BP
Q4S
Q1
Q5N
QF1
Q3BP
Q4S
Modular UPS 2
Modular UPS 1
load
battery
inverter
mains 1
rectifier-
charger
static switch
battery
inverter
mains 1
rectifier-
charger
static switch
mains 2
mains 2
7
6