APC 9000 User Manual

Page of 62
34006452EN/AC
 - Page 38 
Maintenance
Frequency converter or parallel UPS with SSC 
(figure 28)
 
Note:
We recommend that you call on the after-sales support department to carry out these operations.
Static Switch Cubicle 
(figure 29)
 
Note:
We recommend that you call on the after-sales support department to carry out these operations.
During maintenance, the concerned UPS or 
converter must be isolated from Mains 1, its 
battery and the output circuits of the other units.
– inverter isolation
Proceed in the following order:
– shut down the inverter (press the "inverter off" 
button
for 3 seconds),
– open isolating switches Q5N, QF1 and Q1 for 
that line.
The unit is powered down once the capacitors 
have discharged (a few minutes).
In redundant systems with at least one redundant 
UPS, the other UPSs (or converters) ensure 
continuity of power to the load.
In non-redundant systems with a Mains 2, the 
load is supplied by the Mains 2 and the Static 
Switch Cubicle.
In non-redundant systems without a Mains 2, the 
entire system must be shut down.
– start-up
Following servicing, proceed in the following 
order:
– close switch Q1, then switches QF1, Q5N and 
Q4S,
start the inverter (press the "inverter on" 
button
).
Fig. 28: frequency converter exemple
During maintenance, the Static Switch Cubicle 
must be isolated from Mains 2, the load and the 
parallel UPSs.
– if work is required on the control electronics 
alone, open cubicle switch Q4S (but not Q5N) and 
cubicle fuse switches Q1 and Q2. The load can 
then remain supplied by the UPSs. After 
servicing, reclose fuse switches Q1, Q2 and 
switch Q4S.
Caution:
When the Static Switch Cubicle is powered down 
using the above procedure, only the control 
electronics are in fact powered down. The power 
circuits remain energized. Maintenance on the 
static switch power circuits requires shutdown of 
the UPSs and transfer of the load to the 
maintenance bypass line.
– open switch Q5N, then the disconnector-fuses 
Q1 and Q2 in the SSC;
– open switches Q5N, then switch Q4S on all the 
UPSs (figure 29).
Caution:
Even in the maintenance bypass 
configuration, the cubicle is only partially 
shut down and the supply of power to the load 
continues via switch Q3BP.
more extensive maintenance work on the Static 
Switch Cubicle requires the entire system to be 
shut down.
Fig. 29
mains 1
load
mains 1
mains 1
QF1
QF1
QF1
Q1
Q1
Q1
Q5N
Q5N
Q5N
7
6
mains 1
load
mains 1
mains 2
QF1
QF1
Q1
Q1
Q5N
Q5N
Q5N
Q3BP
Q4S