Lucent Technologies Release 7 Manuel D’Utilisation

Page de 2657
DEFINITY Enterprise Communications Server Release 7 
Maintenance for R7r  
555-230-126  
Issue 4
June 1999
Maintenance Object Repair Procedures 
9-748
E-DIG-STA (Emulated Digital Line) 
9
g. The station went off-hook while it was in the ready-for-service state. Use 
the status station command to determine the state of the station. The 
off-hook should have moved the station to ready-for-service. No technician 
action is necessary.
h. No terminal is connected to the Digital Line board. No maintenance action 
is required.
i. The circuit pack’s message buffer is full. This may be caused by having 
many display phones with heavy traffic connected to the circuit pack. No 
action is necessary.
j. Internal system error; no action is necessary. The error counters 1, 2, 3, 4, 
5, 6, 10, 11, 12, 13, 14, 15, and 16 do not have any significance for this 
MO.
System Technician-Demanded Tests: Descriptions 
and Error Codes
Always investigate tests in the order presented in the table below when 
inspecting errors in the system. By clearing error codes associated with the 
Voice and Control Channel Local Loop Around Test, for example, you may also 
clear errors generated from other tests in the testing sequence.
Digital Line NPE Crosstalk Test (#9)
One or more Network Processing Elements (NPEs) reside on each circuit pack 
with a TDM Bus interface. The NPE controls port connectivity and gain and 
provides conferencing functions on a per-port basis. The NPE Crosstalk Test 
verifies that this port’s NPE channel talks on the selected time slot and never 
crosses over to time slots reserved for other connections. If the NPE is not 
working correctly, one-way and noisy connections may be observed. This test is 
part of a port’s Long Test Sequence and takes about 20 to 30 seconds to 
complete. Crosstalk testing occurs on both the primary information channel 
(voice) and the secondary information channel (data) associated with each 
digital station port. If this test fails on either channel, the station and the DTDM 
are taken out-of-service.
Order of Investigation
Short Test 
Sequence
Long Test 
Sequence
D/ND
1
1.
D = Destructive; ND = Nondestructive
Voice and Control Channel Local Loop Around Test (#13)
X
D
NPE Crosstalk Test (#9)
X
ND
Station Lamp Updates Test (#16)
X
ND