Equipment Pack Plumbing Connections
Equipment Pack Specifications
All Inground spas except IGJ-407:
Equipment pack weight = 250 lbs.
IGJ-407:
Equipment pack weight = 300 lbs.
One 2.5 HP heat pump
One 4 HP swim pump
Note: Equipment pack cannot exceed 15 feet from 
spa.
Plumbing Connections
IMPORTANT!  Always  check  local  codes  prior  to  any 
inground spa installation. 
Once the spa and equipment are properly located, you 
will want to lay out the plumbing run.
Trenches  should  be  deep  and  wide  enough  to  allow 
all pipes to be buried below the frost line and should 
be in as straight a line from the spa to the equipment 
as possible. Check local code requirements for under-
ground pipes. Always know what is under the ground 
before you dig anywhere.
You will need 2” flex or PVC lines for your suction, in-
take, and air line. In ground spas have marked intake 
and suction lines, making it easy find and connect to 
and from the spa and equipment pack.
The plumbing run should not be any longer than 15 
feet to maximize water pressure. Another way to max-
imize water pressure is to limit (or even eliminate) the 
use of 90˚ elbows in your plumbing run. A more direct 
plumbing run using 45˚ elbows is more efficient, and 
promotes increased water pressure.
Identifying Plumbing Lines
The  spa’s  plumbing  lines  are  clearly  marked  during 
water testing at the factory. This is done to assist in-
stallers in properly identifying the installation. We still 
recommend  that  the  installers  verify  plumbing  lines 
prior to gluing. This can be done by using one of the 
following techniques. 
Air Test
The  air  test  requires  a  wet/dry  vacuum.  Locate  the 
plumbing line you wish to identify and secure the vac-
uum hose to cut open end. Turn on the vacuum, enter 
the spa and listen for vacuum suction sound from in-
side the spa side filter canister. If you hear the suction 
sound in the canister, the line is properly marked and 
can be connected to the suction side of the pump on 
the equipment pack.
Water Test
The  water  test  requires  a  garden  hose  and  water 
source. Locate the plumbing line you wish to identify 
and secure the outlet side of the garden hose to cut 
open  end.  Turn  on  the  water  supply  to  the  garden 
hose, enter the spa and look for water inside the spa 
side filter canister. If you see water in the canister the 
line is properly marked and can be connected to the 
suction side of the pump on the equipment pack.
If  any  plumbing  line  is  not  properly  marked  or  not 
marked at all, follow either the air or water test proce-
dure until all lines are identified prior to gluing. 
NOTE:  Once  complete,  water  test  the  plumbing  run 
for at least three days prior to covering any plumbing 
trenches and back-filling spa cavity completely. 
NOTE:  Some  local  inspectors  require  pressure  test-
ing the plumbing lines. Although the spa is pressure 
tested  at  the  factory,  local  inspectors  may  insist  on 
pressure  testing  the  plumbing  run  between  the  spa 