Lucent Technologies Release 6 ユーザーズマニュアル

ページ / 453
DEFINITY Enterprise Communications Server Release 6
Installation and Test for Multi-Carrier Cabinets  
555-230-112  
Issue 5
May 1998
Test the System 
Page 4-12
Check Circuit Pack Configuration Again 
4
6. Verify the 
MODE
s of the expansion links have changed.
7. If any problems are indicated, check the TDM cables and the inter- 
cabinet cables in the associated EPN.
Check Circuit Pack Configuration 
Again
1. Verify the screen displays: 
Command:
2. Type list configuration all and press 
Enter
.
3. Verify all circuit packs installed in the system are listed in the reports. Refer 
to 
DEFINITY Enterprise Communications Server Release 6 Maintenance 
for R6r
, to resolve any discrepancies.
System Test Completion
Save Translations
If any administration changes have been made, save and make a back up copy 
of the translations.
Next Steps
After the basic hardware is installed and tested, 3 more steps must be 
completed:
1. Install the telephones and other equipment. See 
Chapter 5, ‘‘Install and 
Wire Telephones and Other Equipment’’
.
2. Administer the features, telephones, and other equipment according to 
customer data on the provisioning plan. The data for system and 
telephone features can be administered using 
DEFINITY Enterprise 
Communications Server Release 6 Administration and Feature 
Description
.
3. After the system is administered, test the telephones and other equipment 
using the procedures in 
Chapter 6, ‘‘Test Telephones and Other 
Equipment’’
.
NOTE:
It may be more efficient to install each hardware component, administer it, 
and test it before going on to install another component.