Before Start-up
Safety
Temporary safety barricades should be placed around any exposed 
openings in the operating (or nonoperating) tower, safety harnesses 
should be worn by personnel where appropriate, and other safety 
precautions should be taken in compliance with OSHA regulations 
and standards.
Cleaning
Clean any nozzles that are clogged. Remove any sediment from the cold 
water basin, sump and screens. Use a water hose to flush cold water 
basins.
If  you  are  restarting  or  recommissioning  a  previously  used  tower,  see 
Warning note on page 17.
Inspection
It is imperative that all operating assemblies be inspected before they are 
placed in operation. The following is a list of components to be checked 
before starting the tower:
• Check  drive  shaft  alignment.  Realign  if  necessary.  See  Marley 
Drive 
Shaft Service Manual.
• Check tightness of bolts that attach mechanical equipment support to 
the tower structure. Check tightness of bolts in fan cylinder joints and 
fan cylinder anchorage. 
• Check concrete structural surfaces for spalling and cracks. Repair as 
necessary.
• Check tightness of the following bolted joints in the fan and drive as-
semblies:
– Fan hub clamp bolts. See Marley 
Fan Service Manual for correct  
torque setting.
– Fan hub cover bolts, where applicable.
– Geareducer
®
 and motor mounting bolts.
– Drive shaft coupling and guard bolts.
• Check Geareducer oil for sludge or water by draining off and testing a 
sample as outlined in the Marley 
Geareducer Service Manual. Check 
Geareducer oil level at “oil level” mark on the side of the case. Add oil 
as required. The oil level placard must be adjusted so that its “full” mark 
is at the same elevation as the “full” mark on the side of the Geareducer 
case. Check oil lines to be sure there are no leaks and all joints are tight. 
 
 Caution