VERTICAL VENT TERMINAL INSTALLATION
WHEN TERMINATING THROUGH A ROOF, THE FOLLOWING 
SPECIFICATIONS PERTAINING TO TERMINAL LOCATION 
MUST BE FOLLOWED.
1.  Proper support must be provided for all pipe protruding through 
the roof.
2.  The vertical roof terminations should be sealed with a plumbing 
roof boot or equivalent flashing.
3.  The  air  intake  termination  and  the  exhaust  vent  termination 
must penetrate the same side of roof.
4.  The center line of the air intake termination and the center line 
of  the  exhaust  vent  termination  must  be  no  closer  than  24” 
(61cm). See Figure 17 and Figure 18.
FLAT ROOF INSTALLATION
On  flat  roof  installations  the  air  intake  and  the  exhaust  vent 
terminations must be a minimum of 24 inches (60 cm) above any 
parapet, vertical wall or structure within 10 feet (3 m) horizontally. 
See Figure 19.