Siemens D410 Benutzerhandbuch

Seite von 150
 
D410 
Commissioning Manual, 08/2008 Edition 
61
 
Commissioning (software) 
4
4.1 
Overview of commissioning 
Prerequisites 
Prerequisites for commissioning the SIMOTION D410: 
●  The system has been connected and wired. 
●  The SIMOTION D410 is switched on and started up (STOP state). 
●  SIMOTION SCOUT (with integrated STARTER) has been installed and started on the 
programming device / PC. 
●  Communication between the SIMOTION D410 and the programming device / PC is 
configured. 
●  You have created a project and installed a SIMOTION D410 in the project. 
 
NOTICE 
 
 
For the SIMOTION D410, a reset of the drive must not be set using the expert list of the 
control unit in the p972 parameter (drive unit reset). This causes SIMOTION D410 
malfunction, the RDY, RUN/STOP and SF/BF LEDs glow red. In this fault situation, the 
SIMOTION D410 must be switched off and on again. 
Commissioning steps 
This chapter describes the steps in configuring the plant and testing the configured stand-
alone drive and axis. The steps in commissioning are listed below in the order as 
recommended:  
1.  Configuring SINAMICS Integrated 
The integrated drive SINAMICS Integrated can be configured in offline or online mode: 
–  Offline configuration 
All components and their order number must be known for the offline configuration.  
–  Online configuration 
The configuration in online mode allows you to upload all information of the connected 
DRIVE-CLiQ components to your user project.