Parallel Operation
9.1
Principle of Operation
PROTECT  1.  has  been  designed  for  parallel  operation  with  n+x 
technology  (“n”  here  stands  for  the  number  of  units  required  for 
load supply, “x” for the degree of redundancy). Up to 3 units of the 
same  type  can  be  connected  in  parallel  here  to  increase  the 
output power and/or achieve higher availability.
NS Hauptverteilung
MI main distribution
USV Einspeisung
UPS feed
Parallelfeld  /  Handumgehung  plus  USV 
Unterverteilung
Parallel  field  /  manual  bypass  plus  UPS 
subdistribution
This results in the following constellations with n+x technology:
1 + 0 Use of 1 unit
max. 10, 15  or 
20 kVA
No redundancy
1 + 1 Use of 2 units
max. 10, 15  or 
20 kVA
Single redundancy
1 + 2 Use of 3 units
max. 10, 15  or 
20 kVA
Double redundancy 
(max. expansion level)
2 + 0 Use of 2 units
max. 20, 30  or 
40 kVA
No redundancy
2 + 1 Use of 3 units
max. 20, 30  or 
40 kVA
Single redundancy 
(max. expansion level)
3 + 0 Use of 3 units
max. 20, 30  or 
40 kVA
No redundancy (max. 
expansion level)