communication  of  the  units  switched  in  parallel  takes  place 
via the 25-pin parallel operation cable(s) included in the scope 
of delivery.
For  this  purpose,  first  remove  the  parallel  port  covers 
(no. 5, p. 26/27)  and  connect  the  UPS  units  with  each  other 
with  one  parallel  operation  cable  each.  Use  one  parallel 
operation cable for 2 units and two parallel operation cables for 
3 units (do not create a ring structure!).
(Communicative) parallel operating connection
... for 2 units:
... for 3 units:
After  connecting  the  parallel  operation  cables,  fasten  the 
previously  removed  parallel  port  covers.  Turn  these  by  180° 
so that the slot of the cover is facing downwards.
The hardware-related installation is now complete.
9.3
Operation of the UPS in a parallel system
The  start-up  process  is  uncomplicated,  does  not  require  any 
prior  knowledge  and  is  basically  oriented  to  the  procedure 
described  in  chapter  6.  If  you  have  obtained  the  parallel 
operation  board  from  AEG  Power  Solutions,  you  can  find 
further  special  instructions  there.  The  displays  in  the  parallel 
system  function  the  same  way  as  described  for  the  individual 
UPS units in chapter 8.
9.3.1
Start-Up
1.
Make  sure  that  all  connections  have  been  made 
according to the installation instructions.
2.
Make sure that all loads are switched off.
3.
Make  sure  that  all  “maintenance  switch” manual 
bypass  switches  (no. 3, p. 26/27)  on  the  back  of