Chapter 4  Installation and Debugging 
4.1  Introduction 
This section outlines the sequence for installing the PSE2500-A3 
device, including plug-in modules, as well as test procedures for 
verifying the integrity of the installation. 
4.1.1  Guidelines 
The device may be installed to allow rear and front access. All 
cables may be routed through conduit openings, and all the operation 
can be completed on the front side. 
4.1.2  EMI Considerations 
When running the dc output cables, pair the positive and negative 
conductors over as much of their length as possible to minimize loop 
areas. 
4.1.3  Installation Tools and Hardware 
You will need the following tools and hardware to install and test 
the PSE2500-A3 unit: 
Wire cutters and strippers 
Heat shrink gun and appropriately sized heat-shrink tubing 
Electric screwdriver with 6 mm (0.24 in.) hex head with 
variable torque range, 0 to 120 in lbs (0 to 13.6 N.m) 
Adjustable wrench 
M8 sleeve