3com PSE2500-A3 Benutzerhandbuch

Seite von 32
User Manual 
PSE2500-A3 External PoE 
Power System 
Chapter 4  Installation and
 Debugging
 
4-3 
Note that the PSE2500-A3 is shipped to the customer site mostly 
pre-assembled so as to minimize the overall installation process. The 
following installation sequence is recommended 
Physical mounting 
Installing rectifiers 
Frame grounding 
Connecting to loads 
Connecting to AC utility/AC grounding 
Initializing the system 
4.2  Physical Mounting 
All items needed for a site are contained within the packing crate. 
The ordered rectifiers may be shipped separately. Please check the 
packing list. 
1)  Place the crate in its vertical position near the installation 
site. 
2)  Carefully remove the crate top and sides and then the 
packing material. If possible, recycle the packing crate and 
the packing material. If not, dispose of properly. 
3) 
Within the packing crate may be the following items: chassis, 
rectifiers, and cables. Remove all this material and place 
aside. 
4) 
Install the chassis into the 19-inch standard cabinet by using 
eight pieces of M6 screws. Notes that use the electric 
screwdriver and correct torque setting (recommend 6.2 to 
6.5 N.m). See figure 4-1.