APPENDIX “A” 
 
THOMSON TECHNOLOGY
©
 
 
 
TYPICAL AUTOMATIC TRANSFER SWITCH 
COMMISSIONING PROCEDURES Model Series TS 870 
 
 
 
Hold the push button “ON” for approximately 5 seconds until the LED light changes state.  Once 
the mode is initiated, the engine will immediately start and the generator will transfer on load as 
previously  described.   
Note:  The  generator  may  or  may  not  transfer  on  load,  which  is 
dependent  on  the  TSC  80  configuration  setting.    The  factory  default  setting  is  for  a  “Load 
Transfer” plant exercise test.  The engine will remain operating on load until the plant exercise 
time delay period expires, then the load will re-transfer back to the utility supply following the 2-
minute utility return timer.  The engine will be automatically re-tested on load every week (i.e.7 
days) at the same time of day that the first test was initiated.  Refer to the TSC 80 manual for 
further information. 
18) On completion of commissioning ensure all controls are left in automatic. 
19) If  required,  forward  document  or  drawing  updates  to  the  equipment  supplier  if  revisions  are 
required and provide the end user with a set of marked-ups to be retained on site. 
20) Ensure copies of manuals for the equipment are on site. 
21) 
Record and forward list of deficiencies to the appropriate parties where applicable.