Quattro DC Startup Guide 
 
 
 
Quattro startup guide  
Initial Inspection  
Unpacking 
1.  When unpacking, check drive for any 
shipping damage. 
2.  The 200A and 250A versions of the 
Quattro arrive in separate shipping 
containers, which require connection in the 
field.  Prior to connecting enclosures, 
check serial numbers on each cabinet 
section to insure mating compatible units.  
Proper mating of enclosures and wiring 
between is important.  Refer to the re-
connection instructions on page 98. 
3.  Review the technical manual, shipped with 
the drive. 
4.  Verify the proper drive model numbers and 
voltage ratings as specified on the 
purchase order. 
5.  Location of the Quattro is important for 
proper operation of the drive and normal 
life expectancy.  
Installation 
The installation should comply with the 
following: 
−  DO NOT mount in direct sunlight, rain or 
extreme (condensing) humidity. 
−  DO NOT mount where corrosive gases or 
liquids are present. 
−  AVOID exposure to vibration, airborne dust 
or metallic particles. 
−  DO NOT allow the ambient temperature 
around the control to exceed the ambient 
temperature listed in the specification. 
Observe the following precautions: 
1.  Wiring guide lines 
 
For Logic Input and Output I/O 
connections, use quality, multi-
conductor cable or discrete stranded 
wire only. 
 
For Encoder and Analog I/O 
connections, use quality, multi-
conductor braided shield cable*. 
 
For Communication I/O connections, 
use quality, multi-conductor braided 
shield* cable or twisted pair wire. 
*Cable shields to be terminated with a 180/360 
degree metal cable clamp attached to Control 
Tray panel flange.  Refer to the EMC 
Compliance on page 97. 
2.  Never connect main AC power to the 
output terminals  
3.  Never allow wire leads to contact metal 
surfaces.  Short circuit may result. 
4.  SIZE OF WIRE MUST BE SUITABLE FOR 
CLASS I CIRCUITS. 
5.  Motor lead length should not exceed 20m 
(60 ft).  If lead length must exceed this 
distance, contact Magnetek for proper 
installation procedures. 
6.  The following are required to be contained 
in individual conduit runs: 3-phase 
incoming power, control power, DC 
armature wires, and DC shunt field. 
7.  Use UL/CSA certified connectors sized for 
the selected wire gauge.  Install 
connectors using the crimping tools 
specified by the connector manufacturer. 
8.  Control wire lead length should not exceed 
20m (60 ft).  Signal leads and feedback 
leads should be run in separate conduits 
from power and motor wiring. 
9.  Verify that the input voltage matches the 
drive’s rating. 
10.  Verify that the motor is wired for the 
application voltage and amperage. 
11.  Tighten all of the three-phase power and 
ground connections.  See Table 1 for 
torque specs. 
 
Wire References 
Torque Specs 
Power Terminals 
56.6 N-m (500 in-lbs) 
Plastic Cover Screws 
0.23-0.28 N-m (2-2.5 
in-lbs) 
Ground Terminals 
31.0 N-m (275 in-lbs) 
Table 1: Input Power Torque Specs 
12.  Check that all control and signal 
terminations are also tight.   
 
CAUTION
: TO PREVENT DAMAGE TO THE 
DRIVE.  THE FOLLOWING CHECKS MUST 
BE PERFORMED BEFORE APPLYING THE 
INPUT POWER. 
−  During shipping, connections may loosen; 
inspect all equipment for signs of damage, 
loose connections, or other defects. 
−  Ensure the three-phase line voltage is 
within 
±10% of the nominal input voltage.  
Also verify the frequency (50 or 60 Hz) is 
correct for the elevator control system.  
−  Remove all shipping devices.  
−  Ensure all electrical connections are 
secure. 
−  Ensure all transformers are connected for 
proper voltage. 