Chapter 4: Installation
4-10
CSX200 Installation Guide
Installing the CSX200 in a 19-Inch Rack
Install the CSX200 in a 19-inch rack as follows:
Position the CSX200 between the vertical frame members of the 19-inch rack.
Fasten the CSX200 with mounting screws as shown in 
Figure 4-8  Installing the CSX200 in the Rack
Complete the installation by connecting power as described in 
, below.
Powering the CSX200
To connect the CSX200 to the power source, perform the following steps:
1.
Plug the power cord into the back panel of the CSX200.
2.
Plug the other end of the power cord into a grounded wall outlet. 
3.
Verify that the PWR LED is on, indicating that the CSX200 is receiving power. After the 
CSX200 runs a self test, the CPU LED blinks green indicating normal operation. If the LED 
remains red, the processor is faulty; contact Cabletron Systems (refer to 
NOTE
The CSX200 has a universal power supply. This allows you to connect the CSX200 to 
power sources of 100–125VAC 50/60 Hz, or 200–240 Vac, 50/60 Hz.
Screws (4)
19-Inch Rack