3.4.6  PHYSICAL CONNECTION TO OMT PC 
 For local commissioning, user can take figure below as a guide to connect the equipment with OMT PC.  
 
Wireless Network/
Ethernet
Wireless
 Build-in 
WCDMA 
Modern 
/Ethernet 
Adaptor
Realize Remote 
Monitoring
Local Monitoring
Wireless 
Modem/Ethernet
Monitoring Center 
RJ45 Cable
 
Figure 7: OMT Connection without Opening Chassis  
 
Note: After connection and commissioning, please make sure the water proof for all external 
connectors. 
 
End of Section 
 
4  COMMISSIONING  
4.1 
PRE-COMMISSIONING TASKS 
After equipment installation, perform the following steps before equipment powering and commissioning: 
 
 
Check the expected voltage, current and power levels do not violate any ratings.  
 
Visually inspect the power connection within the equipment. Ensure that the power cable is correctly 
and securely connected, including grounding wire, RF cable and other cables.  
 
Check grounding connection and verify that the ground resistance is less than 5
Ω. 
 
Test the antenna system and ensure the echo loss within working frequency is less than -14dB 
(VSWR<1.5).