antenna pole and the feeder off the building-top platform. If
the feeder length off the pole is over 5 m, install a grounding
kit before connecting the cabinet jumper. If the length of main
feeder is over 60 m, add a grounding kit in the middle of main
feeder, usually installing one per 20 m.
The outdoor wiring ladder of main feeder must be grounded.
Note:
If the length of feeder is less than 5 m, the ground processing is
unnecessary.
Installing Feeder Grounding Kit
Prerequisite
Install the feeder.
Prepare grounding kits in proper type and quantity as well as
installation tools, such as paper knife, flathead screwdriver,
wrench and sharp-nose pliers.
Steps
1. Select an appropriate installation position for a grounding kit,
and cut off the sheath of feeder according to the size of ground-
ing kit, the structure as shown in
F
IGURE
124 G
ROUNDING
K
IT
S
TRUCTURE
1.
Ground terminal
2.
Ground cable
3.
Feeder
4.
Ground cable circlip
5.
Feeder outer cooper core
6.
Ground cable copper sheet
2. Lead the ground cable of grounding kit towards a ground grid.
The angle between ground cable and main feeder should be not
more than 15°. The orientation of ground cable should comply
with the following specifications:
i.
While installing the antenna feeder system on a tower,
make sure the ground cable of grounding kit downwards
along the tower.
ii. While installing the antenna feeder system atop a building,
lead the ground cable of grounding kit towards a lightning
net.
3. Before installing the grounding kit, in order to enhance sealing
effect and avoid water into feeder inner along the ground ca-
134
Confidential and Proprietary Information of ZTE CORPORATION