e.  Set  the  generator  AUTO-OFF-MANUAL  switch 
to AUTO.
(1)  The generator should crank and start.
(2)  When  the  generator  starts,  an  “engine 
warm-up  timer”  should  start  timing.  After 
about 15 seconds, the transfer relay should 
energize  and  transfer  to  the  “Standby” 
source should occur.
f.  If  transfer  to “Standby”  does  NOT  occur,  check 
the voltage across transfer switch Terminal Lugs 
E1  and  E2.  The  generator  line-to-line  voltage 
should be indicated.
RESULTS:
1.  If normal transfer to “Standby” occurs, discontinue tests.
2.  If transfer to “Standby” does NOT occur and no voltage 
is indicated across Terminal Lugs E1/E2, determine why 
generator AC output has failed.
3.  If  transfer  to “Standby”  does  NOT  occur  and  voltage 
reading  across Terminal  Lugs  E1/E2  is  good,  refer  to 
Flow Chart.
teSt 27 – check manual tranSFer 
SWitch operation
DISCUSSION:
In  automatic  operating  mode,  when  utility  source  volt-
age  drops  below  a  preset  level,  the  engine  should 
crank and start. On engine startup, an “engine warm-up 
timer” on the generator circuit board should start timing. 
When that timer has timed out (about 15 seconds), the 
transfer  relay  should  energize  to  deliver  utility  source 
power  to  the  standby  closing  coil  terminals.  If  normal 
utility source voltage is available to the standby closing 
coil  terminals,  but  transfer  to  Standby  does  not  occur, 
the  cause  of  the  failure  may  be  (a)  a  failed  standby 
closing  coil  and/or  bridge  rectifier,  or  (b)  a  seized  or 
sticking actuating coil or load contact. This test will help 
you evaluate whether any sticking or binding is present 
in the transfer mechanism.
PROCEDURE:
1.  With  the  generator  shut  down,  set  the  generator 
AUTO-OFF-MANUAL switch to OFF.
2.  Set the generator main circuit breaker to OFF or “Open”.
3.  Turn  off  the  utility  power  supply  to  the  transfer  switch, 
using whatever means provided (such as a utility source 
main line breaker).
*
    DaNGEr: Do Not attEmPt maNual 
traNsfEr sWitcH oPEratioN uNtil 
all PoWEr VoltaGE suPPliEs to tHE 
sWitcH HaVE BEEN PositiVElY turNED 
off. failurE to turN off all PoWEr 
VoltaGE suPPliEs maY rEsult iN 
EXtrEmElY HaZarDous aND PossiBlY 
lEtHal ElEctrical sHocK.
4.  In  the  transfer  switch  enclosure,  locate  the  manual 
transfer  handle.  Handle  is  retained  in  the  enclosure 
with a wing nut. Remove the wing nut and handle.
5.  See Figure 2. Insert the un-insulated end of the handle 
over the transfer switch operating lever.
a.  Move  the  transfer  switch  operating  lever  up  to 
actuate the load contacts to the Utility position, 
i.e., load connected to the utility source.
Figure 2. Manual Transfer Switch Operation
MANUAL
TRANSFER
HANDLE
TRANSFER 
SWITCH
OPERATING
LEVER
MANUAL
TRANSFER
HANDLE
TRANSFER 
SWITCH
OPERATING
LEVER
LOAD CONNECTED TO 
UTILITY POWER SOURCE
LOAD CONNECTED TO 
STANDBY POWER SOURCE