9 - GAS SUPPLY PIPING
CAUTION
WHAT TO DO IF YOU SMELL GAS
• Do not try to light any appliance.
• Do not touch any electrical switch; do not use 
any phone in your building.
• Immediately call your gas supplier from a 
neighbor’s phone.  Follow gas supplier’s 
instructions. 
• If you cannot reach your gas supplier, call the fire 
department.
!
  
9.1 Check Gas Supply
TABLE 6: GAS SUPPLY PRESSURE
Natural Gas
4” min. w.c.
10” max. w.c.
LP Gas
10” min. w.c. 
14” max. w.c.
Check line pressure while unit is running in high fire mode.
TABLE 7: GAS PIPING SIZES
Natural Gas
Pipe Length
Pipe Capacity - BTU/Hr. Input Includes Fittings
½”
¾”
1”
1¼”
20’
92,000
190,000
350,000
625,000
40’
63,000
130,000
245,000
445,000
60’
50,000
105,000
195,000
365,000
LP Gas
Pipe Length
Pipe Capacity - BTU/Hr. Input Includes Fittings
Copper Tubing (O.D.)
Iron Pipe
⅝”
¾”
½”
¾”
20’
131,000
216,000
189,000
393,000
40’
90,000
145,000
129,000
267,000
60’
72,000
121,000
103,000
217,000
The length of pipe or tubing should be measured from the gas meter or 
propane second stage regulator.
• Gas pipe to boiler must be correct size for length of 
run and total Btuh input of all gas utilization equipment 
connected to it.  See Table 7 for proper size. 
• Verify your gas line complies with local codes and gas 
company requirements.
• Disconnect boiler and its individual shutoff valve from 
gas supply piping system during any pressure testing of 
system at test pressures in excess of  ½ psig (3.5kPa).
• Isolate boiler from gas supply piping system by closing 
its manual shutoff valve during any pressure testing of 
gas supply piping system at test pressures equal to or 
less than ½ psig (3.5kPa).
• For proper boiler operation line pressure should be 
within minimum and maximum values in Table 6.
• Gas line enters boiler through left side panel. See page 
2 Dimensions and Figure 10.
Boiler is equipped with ½” NPT connection on gas valve for 
supply piping and ½” NPT ball valve for manual shut off. 
Following rules apply:
1. 
Use only those piping materials and joining methods 
listed as acceptable by the authority having jurisdiction, 
or in the absence of such requirements, 
• United States - National Fuel Gas Code, ANSI 
Z223.1/NFPA 54.
• Canada - Natural Gas and Propane Installation Code, 
CAN/CSA B149.1.
2. 
Use pipe joint compound suitable for liquefied 
petroleum gas on male threads only.
3. 
Refer to Figure 10 for general layout, which shows 
basic fittings needed. As shipped, gas line enters 
boiler through right side, as an option, it can be routed 
through either rear or left side panel.
4. 
Use ground joint unions.
5. 
Install sediment trap upstream of gas controls.
6. 
Use two pipe wrenches when making connection to the 
gas valve to keep it from turning.
7. 
Install manual shutoff valve in vertical pipe about 5’ 
above floor outside boiler jacket in addition to shutoff 
valve supplied with boiler.
8. 
Tighten all joints securely.
9. 
Propane gas connections should only be made by 
licensed propane installer.
10. 
Two stage regulation should be used by propane 
installer.
11. 
Propane gas piping should be checked by propane 
installer.
9.2 Connecting Gas Piping