Communication Manager Maintenance-Object Repair Procedures
1066 Maintenance Procedures for Avaya Communication Manager 3.0, Media Gateways and Servers
 
facility is attached. If the NI does not occur at this point, then any cabling between the 
CSU terminals and the NI is also considered to be part of the CPE. This cable typically 
runs between the DS1 facility terminals of the CSU and a cross-connect field where the 
DS1 facility vendor has terminated the DS1 facility. Maintenance responsibility for this 
portion of the DS1 facility resides with the customer unless other arrangements are 
made.
3. If the CPE side LOS indication on CSU B is on (active), check for a problem between the 
CPE side of CSU B and the DS1 converter B circuit pack. Connectors, cables, and the 
CSU B may need to be replaced.
4. If the CSU A and the CSU B do not provide visual CPE side and DS1 facility side LOS 
indications, follow the repair procedure that is given for Error Type1025 (loss of frame 
alignment). Apply the procedure first to the DS1 converter B side instead of the DS1 
converter A where the error is reported (external loop-back test is not expected to pass if 
we execute it at this end as long as we have the LOS indication).
Repair procedure for Error Type #1025 (loss of frame alignment) includes execution of 
the Near-End External Loopback test (#799). If this is not a critical-reliability system and 
if there is only one DS1 facility, then Test #799 can only be executed at the end that is 
closer to the media server relative to the DS1 converter circuit pack at the end of the DS1 
converter complex. If the test cannot be executed for that reason, then still make the 
external loop back as if the test was going to be executed, but instead of executing the 
test, check the green LED at the face plate of the DS1 converter B that is associated with 
this DS1 facility. If the green LED is off, then replace the connectors, cables, and the 
CSU B.
5. If the problem still persists, replace the DS1 converter circuit pack at the other end of the 
DS1 converter complex.
6. If the problem still persists, replace this DS1 converter circuit pack.
If D4 framing is used, an in-band alarm signal (RFA) is transmitted that corrupts transmit 
data in response to this alarm.
k. Error Type 2065: More than 17 misframe errors occurred. This error will clear when there 
are no misframes for 1 hour.
1. Enter display errors and follow the associated repair procedures for any SYNC, 
TDM-CLK, or SNC-BD errors.
2. Verify that the DS1 facility and the network are using the same Line Coding. For TN574 
boards and TN1654 boards in T1 mode, also verify that the Framing Mode used is the 
same. Use list fiber-link and display fiber-link to check the values for this 
DS1 facility. Contact T1 Network Service to check the modes used by the network. See 
the previous sections, “
details on how these options apply to the TN574 and TN1654 DS1 converter boards.
3. For TN574 boards and TN1654 boards in T1 mode, check line equalization settings as 
described in the previous section