Dual-Core Intel Xeon processor LV / E7520 Chipset / 6300ESB ICH
8.0
Debug Procedure
The debug procedure in this section is used to determine baseline functionality for the 
Dual-Core Intel
®
 Xeon
®
 processor LV with Intel
®
 E7520 Chipset and Intel
®
 6300ESB 
ICH Development Kit. This is a cursory set of tests designed to provide a level of 
confidence in the platform operation.
8.1
Level 1 Debug (Port80/BIOS)
Refer to the steps in 
 when debugging a board that does not boot.
8.2
Level 2 Debug (Power Sequence)
Table 23.
Level 1 Debug (Port80/BIOS)
Step
Test
Pass/Fail Criteria
Cause of Failure
1
Verify “SYSTEM PWRGD” LED
Green
Power sequence failure – go 
immediately to Level 2 debug
2
Is “PCI Reset” LED illuminated?
Decimal on Port 80 display 
RED
PCI reset stuck – go to Level 3 debug
3
Verify CPURST LED is off
Off
CPU reset stuck – go to Level 3 
debug
4
Verify Port 80 posting
Port 80 LEDs are posting 
boot codes and stopping
System Hang – Check BIOS go to 
level 3 debug.  Refer to AMI* BIOS 
documentation for details.  
5
Verify BIOS settings
Latest BIOS installed
Contact Intel representative for the 
latest BIOS image
6
Verify default jumper settings
See default settings
Improper jumper settings
Table 24.
Level 2 Debug (Power Sequence)
Step
Test
Pass/Fail Criteria
Cause of Failure
1
Primary power supply voltages
Measure voltages across:
3.3V
-12V
5V
5V
12V
External power supply failure
2
1.8V
1.8V
DDR2 power supply failure
3
1.5V
1.5V
MCH/ICH core power supply failure
4
1.8V VSBY
1.8V
DDR2 standby power supply failure
5
CPU VTT Power Supply
1.05V
CPU_VTT power supply failure
6
CPU0 VRD
1.2V – 1.4V
CPU0 VRD failure
7
CPU1 VRD
1.2V – 1.4V
CPU1 VRD failure
8
Verify “SYSTEM PWRGD” LED
Green
Power sequence failure