Powerware 9390 User Manual

Page of 206
Installing a Remote Emergency Power-Off Control
5-3
Powerware
®
9390 UPS (40–80 kVA) Installation and Operation Manual S 164201535 Rev C
13. If you are installing multiple REPO stations, wire additional stations in parallel with
the first REPO.
14. If required, install wiring from the REPO station to trip circuitry of upstream
protective devices. A normally-open (NO) contact is provided between terminals 6
and 7 of REPO, as shown in Figure 5-1. REPO switch wiring must be in accordance
with UL Class II requirements.
15. When all wiring is complete, reinstall the safety shield panels removed in the
previous steps.
16. Close the control panel door and secure with the retained hardware.
17. Reinstall the door removed in Step 4 and secure with the retained hardware.
18. Close the door and secure the latch.