The following sections only apply to units with an ISDN DBM: 
„
„
„
„
Forcing Backup (Disruptive)
Use this procedure to force backup when network maintenance is planned, when 
equipment problems are reported, or when testing the backup path – whenever 
data needs to be forced from the primary destination interface to the alternate 
destination, typically from the T1 network to the ISDN. 
Procedure
 
1. Make sure the ISDN Link Profiles are set up correctly, Auto Backup is enabled, 
and the ISDN interface is enabled (see 
). 
2. Have someone at the far end disconnect the network cable to initiate backup.
3. Verify that backup is taking place.
NOTE:
When an alarm requiring backup is received, backup can be manually 
controlled by enabling or disabling the Auto Backup option (see 
4. Have the far-end network cable reconnected to return to standard operation.