Chapter 3  Installing the Library
Leveling the Library
24
Quantum|ATL 7100 Series Facilities Planning and Installation Guide
Digital voltmeter (DVM)
ESD protection kit
Leveling the Library
3
To level the library:
1
Move the library onto its designated footprint in the final 
installation area.
2
Lower each foot of the library until it makes contact with the 
floor.
3
Moving in a clockwise direction from the library front, rotate 
each foot clockwise so that each caster is raised approximately 
1/4” off of the floor.
4
Center a carpenter’s level on the top front edge of the library.
5
Check the gauge on the level. If the front of the library is level, 
proceed to step 6. If it is not level:
a
Determine the tilt of the library and adjust the appropriate 
front foot with the wrench, checking the gauge each time 
that a foot is rotated ¼ turn.
b
Repeat step 5 until the front is level, then continue to the 
next step.
6
Center the carpenter’s level on the top left edge of the library.
Note:
Completing this task involves leveling one side of the 
library at a time, moving in a clockwise direction starting 
at the front and ending with the right-side of the library. 
Caution:
When adjusting the feet for leveling purposes, 
DO NOT raise any foot so high that excess weight 
is transferred to any single caster.