Cisco Cisco Process Orchestrator 3.1 User Guide
8-6
Cisco Process Orchestrator 3.1 User Guide
Chapter 8 Monitoring Operations
Monitoring Activity Views
Step 3
Filter the results as necessary (see
Step 4
To view additional information about an instance, highlight it and use one of the following methods to
launch the Process Viewer:
launch the Process Viewer:
•
From the View Results pane, double-click the appropriate process instance.
•
From the Details pane, click any hyperlink (see
).
Modifying Activity View Format
To change an Activity View format, highlight an activity instance, right-click, and choose View >
[Format]. Each of the activity views can display in one of these formats:.
[Format]. Each of the activity views can display in one of these formats:.
Understanding Activity View Indicators
The process and activity views have certain indicators that provide status information.
Status Indicators
The State column displays the status of the individual process and activity. The following indicators
definitions display in the Results pane.
definitions display in the Results pane.
Color Indicators
The colors associated with the individual activities determine the status of the process and activity
instances.
instances.
Activity View
Description
Flat
Displays all process instances and activity instances on the top-level
with no expandable tree view.
with no expandable tree view.
Workflow
Displays the process instances and only one workflow instance (even
if it has run multiple times) in an expandable tree-view format.
if it has run multiple times) in an expandable tree-view format.
Activity (Default view)
Displays the process instances and all related activity instances (no
matter how many times it has run) in an expandable tree-view format.
matter how many times it has run) in an expandable tree-view format.
Status
Description
Succeeded
Process has completed successfully
Running
Process is in progress
Failed (Not Completed)
The process has failed and did not complete the process
execution
execution
Failed (Canceled)
The process has been canceled manually
Indicator
Description
Blue
Process is in progress
Green
Process has completed successfully
Red
Process has failed and did not complete the process execution
Orange
Process has stopped