Cisco Headend System Release 2.7 Release Notes

Page of 20
 
4023675 Rev B 
 
Site Requirements 
 
DNCS and Application Server Hardware Platforms 
Introduction 
This section describes the hardware configurations that are supported by DTACS 
1.2. 
 
DNCS Hardware Configurations 
Ensure your site meets the following DTACS hardware requirements before 
upgrading to DTACS 1.2. The following table lists the minimum requirements for 
the DTACS hardware platforms that are supported by DTACS 1.2. 
DTACS Server 
Platform 
Hard Drive 
Configuration 
Memory 
Processor 
Sun Netra T5440 
 
4 x 146 GB 
 
32 GB 
min. 
 
2 x UltraSPARC T2 1.2 GHz 
8 core 
Sun Netra T5220 
 
2 x 146 GB 
 
8 GB min. 
 
1 x UltraSPARC T2 1.2 GHz 
4 core 
 
 
Scheduling Requirements 
With the live upgrade, your site only needs to be down for 2 to 3 hours during the 
entire upgrade process. Most of the upgrade procedures have no system impact. The 
pre-install and pre-upgrade steps can be performed at any time of day. However, the 
actual upgrade process normally takes place during a maintenance window 
beginning at midnight. The following table provides a breakdown of each upgrade 
process. 
Process 
Length of Time 
Activity 
Pre-install 
1-3 hours 
Activities are performed by Cisco Services, including 
checking the overall health of the system. These 
activities do not impact the system. 
Pre-upgrade 
3-4 hours 
Backing up the system: 
 
Back up the DTACS components 
 
Back up the DNCS and Application Server files 
 
Complete system checks 
These activities do not impact the system.