Cisco Headend System Release 2.7 Release Notes

Page of 32
 
Chapter 2    What Are the Site Requirements? 
 
 
 
18 
4002179 Rev B 
Scheduling Requirements 
With the live upgrade, your site only needs to be down for 2 to 3 hours during the 
entire upgrade process. Most of the upgrade procedures have no system impact. The 
pre-install and pre-upgrade steps can be performed at any time of day. However, the 
actual upgrade process normally takes place during a maintenance window 
beginning at midnight. The following table provides a breakdown of each upgrade 
process. 
Process 
Length of Time 
Activity 
Pre-install 
1-3 hours 
Activities are performed by Cisco Services, including 
checking the overall health of the system. These 
activities do not impact the system. 
Pre-upgrade 
3-4 hours 
Backing up the system: 
 
Back up the system components 
 
Back up the DNCS and Application Server files 
 
Complete system checks 
These activities do not impact the system. 
Upgrade 
6-8 hours total; 
2-3 of these hours 
require system 
outage 
Note: Actual time 
may vary based on 
the number of 
devices being 
upgraded. 
Upgrade the DBDS network: 
 
Back up the DNCS database 
 
Install the DNCS and Application Server 
software 
 
Determine which optional features (licensed or 
unlicensed) need to be enabled as a result of this 
upgrade 
 
Install and download the component software 
(QAM, MQAM, GQAM, and QPSK modulator) 
 
Reboot the hardware 
 
Complete functional checks 
QPSK modulator upgrades and some QAM and 
MQAM upgrades can be completed with little or no 
subscriber impact. However, 2-3 hours of the 
upgrade require system outage. 
Post-Upgrade 
3-4 hours 
Back up the system: 
 
Back up the file system 
 
Back up the DNCS database 
These activities do not impact the system.