Method of Procedure 
Introduction 
RFN_3.1 Beta
 
Preparation of a site and installation of equipment requires close coordination 
between RFN, RFN’s customer and its customers, and designated third-party 
RFN Certified Integration Partner(s). Domains of responsibilities are shown in the 
following table. 
 
Task 
Responsible Party 
Prepares system design and quotes 
RFN Customer 
Provides Project Management, including site survey 
RFN Customer 
Constructs site, including racks, ironwork (ceiling support, 
ladder racks, etc.), AC power, DC power, and battery 
backup systems. 
RFN Customer/Customer 
Lays conduit and cable, installs new fiber raceways, and fire 
stopping after cables have been laid. 
RFN Certified Integration Partner 
Installs, tests, and commissions RadioFrame Networks 
equipment, including site acceptance. 
RFN Certified Integration Partner 
Maintains RadioFrame Networks equipment, including 
logbook. 
RFN Customer/Customer 
1.1.2 Site 
Documentation 
The following documents are required for installing, commissioning, testing, and 
maintaining RadioFrame Networks equipment. Some or all of this documentation 
will be left on site. In addition, a logbook will be stored on site that will be used for 
tracking all changes, updates, and maintenance work done on RadioFrame 
System equipment. 
 
Document 
Site Survey 
Pre-Installation Checklist 
Equipment Inventory 
Site Acceptance Test 
Equipment Functionality Acceptance Test 
Site As-built 
Site As-built Acceptance Test 
Equipment As-built 
Equipment As-built Acceptance Test 
Alarms 
Alarm Procedures