MC-Series System Installation & Testing 
Pre-Installation 
34 
RadioFrame Networks, Inc.
 
3.1.3 Anchoring 
Anchor the MC-Series System cabinet to the floor using suitable anchors (Hilti or equal). Do not 
mount the MC-Series System cabinet on casters. 
3.1.4 
Seismic Zone Installation 
All RadioFrame Networks equipment is seismically rated to withstand vibrations of a Level 4 
earthquake. The property owner is responsible for any damage to RFN equipment due to building 
or cabinet structures that are not rated to withstand vibrations of a Level 4 earthquake, or not 
secured to withstand vibrations of a Zone 4 earthquake.  
Ensure that a certified architect specializing in earthquake-resistant installation provides seismic 
designs and recommendations in areas where the potential loss of the site may outweigh 
associated costs of earthquake-resistant design. PE stamped drawings shall be provided before 
the installation proceeds. 
3.1.5 
Cooling of Equipment 
Ensure that the location provides sufficient cooling for the MC-Series System cabinet. Refer to 
section 2.5.8 Heat Load for BTUs generated by the MC-Series System.  
3.1.6 Power 
Ensure that a DC power source is available that can supply full power requirements for both the 
MC-Series System cabinet and all ancillary equipment for the installation. This power source may 
be a bulk DC power source, an internally mounted DC powerplant, or an external DC powerplant. 
For internal or external DC powerplants, backup batteries may or may not be required, depending 
on whether or not the powerplant is driven from a UPS (Uninterruptible Power Supply). Refer to 
Nextel standards for DC power design. 
Any installation of AC power conductors shall be done by a licensed, bonded, and insured 
electrician. Follow standard Nextel design practices for AC and DC power circuits including any 
required AC surge protection. Identify any contract labor and materials required. 
Refer to section 2.5 Specifications for DC power requirements. Plan to use termination lugs. 
Required crimp tool is CT-1700. 
3.1.7 Grounding 
The MC-Series System cabinet must be grounded to either a defined equipment grounding 
system in a Nextel facility or to the building grounding electrode in a customer facility. Plan to 
install a grounding system for the MC-Series System cabinet and ancillary hardware. Refer to 
Chapter 7 and Appendix C of Motorola R56, as modified by Nextel, for grounding standards. The 
Master Ground Bar (MGB) will be installed on the wall on the telco board. Plan to use termination 
lugs. Required crimp tool is CT-1700.