MC-Series System Installation & Testing 
Pre-Installation 
36 
RadioFrame Networks, Inc.
 
3.2  Scheduling / Logistics 
a.  Procure all non-RFN hardware. Refer to Nextel documentation for procurement of iSC-3s, 
EAS, and CSU. 
b.  Procure the materials identified in 3.1 required by Nextel technicians to complete the 
installation. 
c.  Initiate the contracts necessary to engage outside contractors to complete the installation 
work necessary, including any design or engineering work necessary for seismic areas. As 
noted previously, any installation requiring seismic certification requires a formal design and 
installation package from an architect skilled in this area. 
d.  Follow standard Nextel RF Operations and Site Development procedures for scheduling (a) 
all installation activity and (b) all necessary datafill work. 
 
Planning should now be complete for the following tasks:  
•  Securing the MC-Series System cabinet to the mounting surface 
•  Installing AC or DC power cabling and DC powerplant 
• Installing 
grounding 
• Installing 
T1 
cabling 
•  Installing a GPS antenna system 
•  Installing facility alarms 
• Adding 
HVAC 
 
3.3  MC-Series System Installation Kit 
RadioFrame Networks provides the following materials in an installation kit shipped with the  
MC-Series System: 
 
Qty 
Item 
Usage 
GPS surge arrestors, 2.4 GHz bulkhead N-type, inline 
TOR 
RG58/U, 1 meter coax cable, BNC M to BNC M 
BIC to iSC 
LMR-195-PVC, 84” cable, N-type 
iSC to GPS at TOR 
20 
10/32 Philips thread cutting screw 
mounting non-RFN HW in rack 
Lifting eyelet bolt 
cabinet installation 
Non-disposable ESD wrist strap 
ESD prevention 
Cabinet manufacturer’s installation manual 
mounting cabinet 
SMA terminators 
spares for RF shelf reconfigurations