MC-Series System Installation & Testing 
Installation 
38 
RadioFrame Networks, Inc.
 
4 Installation 
4.1 Site 
Inspection 
Following all construction work, both exterior and interior, the site and facility shall be in a suitable 
condition for the installation of communications equipment.  
In general, the following considerations need to be observed: list section 3.1 items except T1 
•  Facility is secured with lockable doors. 
• HVAC 
• Grounding 
•  Interior of facility shall be free of excessive dust. 
• All refuse related to the installation tasks shall be removed. 
 
Consideration should be exercised when laying out a site to allow primarily for all code 
requirements for spacing, and then the most efficient use of space. Special attention shall be 
given to future expansion with regard to cable runway heights, electrical outlet
 
placement, and 
equipment placement. 
4.2  Receipt of Equipment 
The MC-Series System is provided pre-installed in a standard 79” tall, 19” wide EIA- compliant 
cabinet with the following equipment: 
•  BIC (BTS Interface Chassis) 
•  AIC (Airlink Interface Chassis) 
•  RBS (RadioBlade Shelf) 
•  RF Shelf (3 each) 
•  PDU (Power Distribution Unit) 
•  MC-Series System Installation Kit 
4.2.1 Equipment 
Inspection 
Inspect the equipment immediately upon receipt. If obvious damage has occurred to the shipping 
container before unpacking, contact the shipping agent. Ask that a representative of the shipping 
company be present while the equipment is unpacked.  
Check for the following: 
•  loose or damaged equipment in the pre-installed cabinet 
•  dents, scratches, or other damage on all sides of each component 
 
If any equipment is damaged, contact the shipping company immediately, then a Nextel 
representative.