Table 4: Commissioning Task Explanation
Commissioning Tasks
Observation
1. Isolation detection
Detect isolation of service antenna and donor antenna.
2. Set control channel
frequencies
Enter the center frequency of the main control channel, the
commissioning guide will provide recommended DL/UL gain settings
based on main control channel input power and the total channel
numbers.
commissioning guide will provide recommended DL/UL gain settings
based on main control channel input power and the total channel
numbers.
Users can skip this step and directly finish the commissioning guide
even if the frequency information or the total channel numbers are
unknown. Users are able to set the DL/UL gain manually any time
after the isolation detection has been completed and passed.
even if the frequency information or the total channel numbers are
unknown. Users are able to set the DL/UL gain manually any time
after the isolation detection has been completed and passed.
3. Set Channel No.
Enter the total channel numbers
4. Recommended DL and UL
gain parameters
The commissioning guide will provide recommended DL/UL gain
settings.
settings.
Users will still need to set
all the gains manually in the “Device” pages,
and the frequencies for all the independent channels in the same
“Device” pages after the commissioning process is finished.