Mounting IBR – Location & Bracket 
IBR must be mounted on a suitable bracket that will hold IBR securely under all environmental conditions. 
•  When mounting on a mast, ensure that the mast has a diameter of between 50 mm to 115 mm (2” to 
4.5”), or else a collar may be required to adapt to the mast bracket. 
•  Fasten the mast bracket onto the mast using the enclosed stainless steel bands 
•  Fasten the alignment bracket onto front part of the mast bracket using the enclosed stainless steel 
screws, nuts and washer (M6 size screws which require a 4.5mm Allen Key tool which is included). To 
adjust and lock the bracket using the M8 alignment bolts, a 6mm Allen Key tool is required. 
NOTE:  Do not use zinc-plated screws / bolts as these will corrode and endanger link performance and safety to 
people and equipment.  
5.3.1  Mounting Location - Choosing the best possible mounting location for IBR is important for safety, security, 
and link performance. 
•  Install IBR in a location where access is restricted to authorized service personnel. 
•  Select a location that is within one hundred meters of a power source if using PoE
+
•  Avoid locations that might present hazards to installation or maintenance crews. 
5.3.2  Fastback Networks’ Articulating Bracket - Fastback Networks offers an articulating mount that can be 
mounted on walls or masts and adjusted up to + 45 degrees in elevation and azimuth in 15 degree 
increments.   The figure below shows the mounting bracket alone and mounted on IBR-1301. 
Figure 9 - IBR with Mounting Bracket 
                  
 
Pole bands can be installed on the bracket if required. 
Figure 10 – IBR Mounted on Pole