13.4  Battery Management
The Battery Management page is used to configure, run and review the results of 
battery testing.
The testing performed verifies that the battery voltage holds up above a specified 
voltage for the duration of the test.
 
Figure 21 - Battery Management WEB Applet (typical)
The controls are as follows:
Minimum Voltage.  This is the voltage that will be applied to the rectifiers for the 
duration of the test.  The battery voltage will be monitored and if it falls to within 
2% above the minimum voltage, the test will be terminated and be considered to 
have failed.
Test Time (mins).  The duration that the test should be run for (in minutes).
Days between tests.  The number of days between subsequent periodic tests.
Time of day for test.  The hour and minute to start the testing.  This is usually set 
to be an off peak time.
Enable periodic Test checkbox.  Check this box to enable automatic periodic 
testing to run.
Enable battery test.  Check this box to enable any form of battery testing.  This 
control acts as a lock to prevent inadvertent testing.