Installation, connecting up, commissioning 
 
3.2 Installing and commissioning the CP 
CP 1242-7 
Operating Instructions, 03/2012, C79000-G8976-C247-03 
31
 
Table 3- 2 
Procedure for installation and connecting up 
Step 
Execution 
Notes and explanations 
Mount the CP on the DIN rail and connect it to 
the module to its right. 
Use a 35 mm DIN rail. 
The slots to the left of the CPU are permitted. 
Secure the DIN rail. 
 
Secure the power supply wires to the power 
output of the CPU. 
 
Secure the wires of the power supply to the 
plug supplied with the CM and insert the plug 
in the socket on the top of the CM. 
The pinning is shown beside the socket on the top of the 
housing. You will also find this in the section Pin assignment of 
Connect the antenna to the SMA socket of the 
CP. 
Lower surface of the CP 
Notice 
  Protect the antenna connector using suitable overvoltage protection equipment if the antenna cable is 
longer than 30 m. 
  Protect the antenna connector with suitable lightning protection if you install the antenna outdoors. 
Turn on the power supply. 
 
Close the front covers of the module and keep 
them closed during operation. 
 
The remaining steps in commissioning involve 
downloading the STEP 7 project data. 
The STEP 7 project data of the CP is transferred when you 
load to the station. To load the station, connect the 
engineering station on which the project data is located to the 
Ethernet interface of the CPU. 
You will find more detailed information on loading in the 
following sections of the STEP 7 online help: 
  "Loading project data" 