HP Performance Optimized Data Center (POD) 240a User Manual

Page of 93
 
Maintenance  79 
Power up procedure 
Standard power up procedure 
This procedure is for reference only and assumes that the POD is fully commissioned and powered up by HP 
before being turned over to you. 
Before you begin the power up procedures in this section, verify that the POD is not in operation and that the 
internal ambient temperature of the POD is greater than 10ºC (50ºF). If the internal ambient temperature of 
the POD is less than 10ºC (50ºF), see "Cold weather power up procedure (on page 
)." 
This process helps to be sure that personnel are safe during the electrical power up of the HP POD 240e NA. 
  
 
WARNING:
  To avoid risk of personal injury or loss of life, do not open an energized POD 
electrical cabinet without an energized work permit and appropriate PPE. 
  
 
Power up checklist 
Site electrical 
 
Verify that all site POD critical IT feeder supply breakers are open. 
 
Verify that all site Adiabatic mechanical feeder supply breakers are open. 
POD electrical 
 
Service aisle—Verify that all site Adiabatic unit service disconnects are open. 
 
Hot aisle—Verify that all IT power drop box breakers on the power tap boxes are open. 
  
 
IMPORTANT:
  Following these steps prevent any possibility of energizing the IT load. 
  
 
IT sections A and B: 
a. 
Close all non-spare breakers and fuses within the control cabinet. 
b. 
Close and latch the control cabinet. 
c. 
Position the EPO system (on page 
) to Armed (white) or Bypass (green). 
d. 
Verify that all EPO activation buttons are in the reset position (not depressed). 
 
IT critical power feed cabinets A and B: 
a. 
Close all non-spare breakers within primary A and B and secondary A and B power supply 
cabinets. 
b. 
Close and lock electrical cabinet doors. 
c. 
Close all Adiabatic power supply feeder breakers in both the primary mechanical and secondary 
mechanical cabinets. 
d. 
Close and lock Adiabatic primary mechanical and secondary mechanical cabinets. 
 
Standard power up procedure 
Perform the following procedures in the exact order in which they are listed.