Site plan requirements and actions  22 
Site plan requirements and actions 
Completing a site assessment 
HP requires a detailed assessment before planning and preparing your site location for the HP POD 240e 
NA. Consult with HP to schedule a site assessment. 
A standard site assessment visit includes the following tasks: 
 
Selecting an appropriate site for the HP POD 240e NA 
 
Assessing the proposed site for: 
Measurements for clearances 
Infrastructure for the final solution 
Access to utilities 
Site pad 
Installation considerations, including locations for delivery trucks, large installation equipment (such 
as cranes), and storage 
Electrical infrastructure 
Facility network and access control systems 
 
Developing an engagement plan and verifying your contacts 
 
Discussing future development and growth plans 
For a complete site assessment checklist, see "Appendix A: HP site assessment (on page 
)." 
 
HP Site Preparation Drawing Package 
After receiving a signed purchase agreement, HP provides detailed engineering drawings. These drawings 
contain information to assist you and your MEP team to prepare the site for POD installation. If there are 
areas of special interest, HP can work directly with your MEP team to provide additional assistance. 
 
Zoning and permit requirements 
You are responsible for compliance of the overall installation in accordance with all local and national 
regulations, ordinances, codes, and the product specifications. 
 
Project coordination 
Your Project Manager must perform the following tasks: 
 
Coordinate with all trades before installation to be sure that trade conflicts are resolved. 
 
Coordinate the installation and integration of all systems. 
 
Be sure that the site safety and security programs are properly administered.